Main navigation | Section navigation | Content

The Lincoln Hall Project « College of Liberal Arts & Sciences « University of Illinois


Lincoln Hall Project


Renovation Photos

 

Photos with brief progress reports showcase Lincoln Hall as it moved through various construction phases.

August 2013
The Lincoln Hall time capsule was installed on Friday, August 16, 2013.

time capsule time capsule time capsule time capsule time capsule time capsule

February 2013
The Lincoln Hall Rededication ceremony was held on Abraham Lincoln’s birthday, Tuesday, February 12, 2013—exactly 100 years to the day of the building’s original dedication.

Rededication Frerichs Watkins Kennedy Quinn Speakers Underwood Easter Wise Ribbon cut Watts Davis Black Chorus Black Chorus Governor Quinn Tour

October 2012
An estimated 2,000 people visited the Lincoln Hall Open House on October 27, 2012, during Homecoming.

Memorial Hall LAS dean, Lincoln bust Storyography Scroll capsule Harrison Honors time capsule Alma Scholars crowd Marching Illini ceremony sealing signatures Theater

July 2012
The Lincoln bust returned to its niche in the Memorial Hall entrance of Lincoln Hall.

lobby bust media bust-bolt bust-back bust-niche

March 2012
The theater is nearly done and progress on the landscaping, particularly in the courtyard, has proceeded rapidly.

lobby theater basement courtyard plants courtyard plants courtyard plants

February 2012
The focus is on the first floor classrooms and the courtyard even as upper floors are still receiving finishing details.

courtyard entrance courtyard pavers boards classroom floor entrance bathroom third floor

January 2012
New seats are being installed in the theater as the renovation enters its final few months.

theater seats trim staircase heating system classroom classroom

December 2011
The last of the phone cable was installed and finish work is in full force on the second floor and in the theater.

cable brackets

November 2011
A focus has been on repairing the copper brackets on the roof overhang as the basement takes shape.

brackets brackets brackets front of Lincoln Hall railing in front of Lincoln Hall basement basement basement basement window
  painting

October 2011
Work is progressing at full speed on the interiors.

painting plaster wall wall wall wall wall cafe cafe steps

September 2011
The new decks in the courtyard are taking shape while creating the offices and spaces for the building’s new mechanical systems continues.

airhandler  concrete  airhandler  basement   concrete  concrete 

August 2011
The medallions and other ornamental plaster in the theater are also being restored to their original condition and coloring.

plaster  basement  plaster  plaster  concrete  concrete 

July 2011
Painters are restoring the foyer to its original grandeur using gold paint and gold leaf.

basement   plaster  basement  basement  

June 2011
Heavy rain in June slowed down the work on the exterior of Lincoln Hall but didn’t dampen the progress on the interior.

basement  concrete mixer  courtyard  skylights  foyer  wiring  third floor rooms 

May 2011
A focus of attention for crews are the new floors that wil occupy the former flyspace above the Lincoln Hall Theater stage. Exterior work, such as in the courtyard, is also moving forward at full speed.

dust forms rays of light  cutting concrete  cutting concrete  workders  workers  workers  tradesman carries wooden beams  workders  workers 

April 2011
Drywall is going up on the fourth floor as tuckpointing resumes on the exterior.

steel girders  mudding drywall  hallway  tuckpointing the exterior of the theater  tuckpointing the exterior of the theater  construction plans

March 2011
Window openings are being framed to accommodate new windows, and walls are taking shape for dozens of rooms on the second floor.

window framing  block wall  window framing  window framing window framing  insulation 

February 2011
The mechanical and drywall contractors have moved on to the second floor, where the framing is nearly complete and they are finishing the installation of ductwork and piping.

ductwork  framing  piping  framing  courtyard 

January 2011
Contractors made significant progress in excavating the basement, which must be deepened by several feet in order to accommodate the new heating and cooling systems. The workers have also been laying concrete block and installing drywall on the upper floors. In many areas it is now possible to imagine how some of the finished spaces will look. Other areas still appear eerily different.

basement  excavation  jackhammer  wall studs  wall studs  tubes  theater  walls  conduit  hallway 

December 2010
Plumbers continued to rough in the plumbing on the first, second, and third floors while area wells were excavated on the east exterior of the building (Quad side). The building is being enclosed for the winter, with temporary steam and electric powered heaters being installed throughout.

pipefitting drilling hole  drilling hole   foundation  

November 2010
Work continued on the roof as new slate tiles were nailed to the roof. The contractors also continued with the ventilation, mechanical, and plumbing work. Insulation and fire proofing was completed on the fourth floor.

crane  nailing roof tiles  flashing 

October 2010
Unless you had performed on the stage in the Lincoln Hall Theater, you might have never noticed the three-and-a-half-story wall that formed a curved backdrop. This cyclorama was once a popular way of projecting backdrops, such as skies, for scenes. Workers dismantled the structure, which will be replaced by more modern, less space-consuming, technology.

cyclorama  cyclorama  third floor  duct work  piping

September 2010
Nearly 95% of the wood trim, doors, and frames have been removed. And at this point, nearly 95% of all materials removed from the job have been recycled or given to local organizations. Many areas of the fourth floor have been roughed in with studs and walls, plumbing and electrical.

fourth floor  fourth floor

August 2010
The exterior of Lincoln Hall receives a facelift as workers from Mid-Continental Restoration grind out worn mortar between bricks prior to repairing it. The masons completed training in historic masonry techniques before beginning the work so that they would tool the mortar in the manner consistent with the practices common a century ago. New slate tiles were hauled up to the roof.

Tuckpointing   Tuckpointing   New Slate Tiles   New Slate Tiles

July 2010
Began removing theater chairs; the ornate endcaps were set aside so they can be reused in the theater.

Chairs were removed from the old theater.   The ornate endcaps were set aside so they can be reused in the theater.   A nearly empty theater.

May 2010
Completed electrical and wall demolition in the basement. Demolition continues on the other floors and includes the removal of the wood trim. Continued demolition in the basement and 4th floor. Protection of historic areas. Removal of historic fixtures.

Completed electrical and wall demolition in the basement. Demolition continues on the other floors and includes the removal of the wood trim.   Continued demolition in the basement and 4th floor.  Protection of historic areas. Removal of historic fixtures.

April 2010
Demolished pipes in the basement and removed lights. Knocked down walls and removed ceilings on the 4th floor. Completed laydowns and preliminary demolition.

Demolished pipes in the basement and removed lights. Knocked down walls and removed ceilings on the 4th floor.   Completed laydowns and preliminary demolition.